Esta Skill de Claude genera informes exhaustivos del estado de los proyectos analizando artefactos existentes, como cartas de constitución y backlogs, para calcular métricas e identificar bloqueos. Resume el progreso utilizando indicadores RAG para cronograma, alcance, presupuesto y calidad. Úsela al final de los sprints, antes de las reuniones de gobierno o cuando surjan nuevos riesgos para proporcionar actualizaciones a las partes interesadas.
Instalación rápida
Claude Code
Recomendadonpx skills add pjt222/agent-almanac -a claude-code/plugin add https://github.com/pjt222/agent-almanacgit clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/generate-status-reportCopia y pega este comando en Claude Code para instalar esta habilidad
Documentación
Generate a Project Status Report
Produce a periodic status report by analyzing project artifacts, calculating progress metrics, and summarizing accomplishments, blockers, and upcoming work with RAG (Red/Amber/Green) health indicators.
When to Use
- End of sprint or reporting period (weekly, biweekly, monthly)
- Stakeholder requests for project health update
- Before steering committee or governance meetings
- When project health indicators change (e.g., new blocker or risk materializes)
- Periodic checkpoint against charter milestones
Inputs
- Required: Reporting period (start date, end date)
- Required: At least one project artifact (BACKLOG.md, SPRINT-PLAN.md, WBS.md, or PROJECT-CHARTER.md)
- Optional: Previous status reports (for trend comparison)
- Optional: Budget or resource tracking data
- Optional: Risk register updates
Procedure
Step 1: Read Existing Artifacts
Scan the project directory for PM artifacts:
- PROJECT-CHARTER.md — milestones, success criteria
- BACKLOG.md — item counts by status, burn-down data
- SPRINT-PLAN.md — sprint goal, committed items, task completion
- WBS.md — work package completion percentages
- Previous STATUS-REPORT-*.md files — trend data
Read available files. Not all will exist — adapt the report to available data.
Got: At least one artifact read successfully, key metrics extracted.
If fail: If no artifacts exist, report cannot be generated. Create a charter or backlog first using the draft-project-charter or manage-backlog skills.
Step 2: Calculate Progress Metrics
Compute metrics from available data:
Agile metrics (from BACKLOG.md / SPRINT-PLAN.md):
- Velocity: story points completed this sprint
- Sprint completion: items done / items committed
- Backlog burn-down: total remaining points vs previous period
- Cycle time: average days from In Progress to Done
Classic metrics (from WBS.md):
- % complete: work packages done / total work packages
- Schedule variance: planned milestone dates vs actual
- Effort variance: estimated effort vs actual effort consumed
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
Got: 3-5 metrics calculated with previous period comparison.
If fail: If no historical data exists (first report), omit Previous and Trend columns. If data is incomplete, note gaps in report footer with action items to establish tracking.
Step 3: Identify Blockers, Risks, and Issues
List active blockers and risks:
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
Cross-reference against the charter risk register. Flag any new risks not previously identified.
Got: All active blockers and top risks documented with owners and actions.
If fail: If no blockers exist, explicitly state "No active blockers" — don't leave the section empty. If a blocker lacks an owner, escalate to project manager for assignment.
Step 4: Summarize Accomplishments and Next Period Plan
Write two sections:
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
Got: 3-5 accomplishments with concrete evidence, 3-5 planned items for next period.
If fail: If no accomplishments exist, report the reason (blocked, re-planning, team unavailable). If next period plan is unclear, list "Planning session scheduled for [date]" as the primary item.
Step 5: Assign RAG Indicators and Write Report
Assess project health across four dimensions:
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
Write the complete report:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
Save as STATUS-REPORT-[YYYY-MM-DD].md.
Got: Complete status report saved with RAG indicators, metrics, and narrative.
If fail: If data is insufficient for RAG assessment, use ⚪ (Grey) indicating "insufficient data" and list what data needs to be collected for next report.
Validation
- Status report file created with correct date-stamped filename
- RAG indicators assigned for all four dimensions with justification
- At least 3 metrics calculated from project artifacts
- Blockers section present (even if "No active blockers")
- Accomplishments listed with evidence
- Next period plan included
- Executive summary is 2-3 sentences, not a paragraph
- Every blocker and risk has an owner and action with deadline
Pitfalls
- Report without data: Status reports must be evidence-based. Every claim should reference an artifact or metric.
- All green, all the time: Persistent green RAG without evidence suggests the report isn't honest. Challenge green assessments.
- Blocker without owner: Every blocker needs an owner and an action. Unowned blockers don't get resolved.
- Metric without context: "Velocity = 18" means nothing without comparison. Include previous period or target.
- Too long: A status report should be scannable in 2 minutes. Keep it to 1-2 pages.
- Missing decisions section: If the project needs stakeholder decisions, make them explicit with deadlines.
- Stale data: Using outdated artifacts leads to misleading reports. Verify artifact dates match reporting period.
- Missing trend data: First-time reports can't show trends, but subsequent reports must compare to previous periods.
Related Skills
draft-project-charter— charter provides milestones and success criteria for status trackingmanage-backlog— backlog metrics feed the status reportplan-sprint— sprint results provide velocity and completion datacreate-work-breakdown-structure— WBS completion drives classic progress metricsconduct-retrospective— status report data feeds the retrospective
Repositorio GitHub
Habilidades relacionadas
content-collections
MetaEsta habilidad proporciona una configuración probada en producción para Content Collections, una herramienta centrada en TypeScript que transforma archivos Markdown/MDX en colecciones de datos con tipado seguro mediante validación Zod. Úsala al construir blogs, sitios de documentación o aplicaciones Vite + React con mucho contenido para garantizar seguridad de tipos y validación automática de contenido. Abarca todo, desde la configuración del plugin de Vite y compilación MDX hasta la optimización de despliegue y validación de esquemas.
polymarket
MetaEsta habilidad permite a los desarrolladores crear aplicaciones con la plataforma de mercados de predicción Polymarket, incluyendo la integración de API para operaciones y datos de mercado. También proporciona transmisión de datos en tiempo real a través de WebSocket para monitorear operaciones en vivo y actividad del mercado. Úsela para implementar estrategias de trading o crear herramientas que procesen actualizaciones de mercado en tiempo real.
creating-opencode-plugins
MetaEsta habilidad ayuda a los desarrolladores a crear complementos de OpenCode que se conectan a más de 25 tipos de eventos, como comandos, archivos y operaciones LSP. Proporciona la estructura del complemento, las especificaciones de la API de eventos y los patrones de implementación para módulos en JavaScript/TypeScript. Úsala cuando necesites interceptar, monitorear o extender el ciclo de vida del asistente de IA de OpenCode con lógica personalizada basada en eventos.
sglang
MetaSGLang es un framework de alto rendimiento para el servicio de LLM que se especializa en generación rápida y estructurada para JSON, expresiones regulares y flujos de trabajo de agentes utilizando su caché de prefijos RadixAttention. Ofrece una inferencia significativamente más rápida, especialmente para tareas con prefijos repetidos, lo que lo hace ideal para salidas complejas y estructuradas, y conversaciones multiturno. Elige SGLang sobre alternativas como vLLM cuando necesites decodificación restringida o estés construyendo aplicaciones con uso extensivo de prefijos compartidos.