Conduct a Retrospective
Facilitate a structured retrospective that reviews recent project execution, identifies what worked and what didn't, and produces actionable improvement items that feed back into project processes. This skill transforms raw project data into evidence-backed learnings with specific actions, owners, and due dates.
When to Use
- End of a sprint (sprint retrospective)
- End of a project phase or milestone
- After a significant incident, failure, or success
- Quarterly review of ongoing project processes
- Before starting a similar project (lessons learned review)
Inputs
- Required: Period under review (sprint number, date range, or milestone)
- Optional: Status reports from the review period
- Optional: Sprint velocity and completion data
- Optional: Previous retrospective actions (to check closure)
- Optional: Team feedback or survey results
Procedure
Step 1: Gather Retrospective Data
Read available artifacts from the review period:
- STATUS-REPORT-*.md files for the period
- SPRINT-PLAN.md for planned vs actual
- BACKLOG.md for item flow and cycle times
- Previous RETRO-*.md for open action items
Extract key facts:
- Items planned vs completed
- Velocity trend
- Blockers encountered and resolution time
- Unplanned work that entered the sprint
- Open action items from previous retrospectives
Got: Data summary with quantitative metrics (velocity, completion %, blocker count).
If fail: If no artifacts exist, base the retrospective on qualitative observations.
Step 2: Structure "What Went Well"
List 3-5 things that worked well, with evidence:
## What Went Well
| # | Observation | Evidence |
|---|------------|---------|
| 1 | [Specific positive observation] | [Metric, example, or artifact reference] |
| 2 | [Specific positive observation] | [Metric, example, or artifact reference] |
| 3 | [Specific positive observation] | [Metric, example, or artifact reference] |
Focus on practices to continue, not only outcomes. "Daily standups kept blockers visible" is more actionable than "We delivered on time."
Got: 3-5 evidence-backed positive observations.
If fail: If nothing went well, look harder — even small wins matter. At minimum, the team completed the period.
Step 3: Structure "What Needs Improvement"
List 3-5 things that need improvement, with evidence:
## What Needs Improvement
| # | Observation | Evidence | Impact |
|---|------------|---------|--------|
| 1 | [Specific issue] | [Metric, example, or incident] | [Effect on delivery] |
| 2 | [Specific issue] | [Metric, example, or incident] | [Effect on delivery] |
| 3 | [Specific issue] | [Metric, example, or incident] | [Effect on delivery] |
Be specific and factual. "Estimation was off" is vague. "3 of 5 items exceeded estimates by >50%, adding 8 unplanned days" is actionable.
Got: 3-5 evidence-backed improvement areas with stated impact.
If fail: If the team claims everything is fine, compare planned vs actual metrics — gaps reveal issues.
Step 4: Generate Improvement Actions
For each improvement area, create an actionable item:
## Improvement Actions
| ID | Action | Owner | Due Date | Success Criteria | Source |
|----|--------|-------|----------|-----------------|--------|
| A-001 | [Specific action] | [Name] | [Date] | [How to verify success] | Improvement #1 |
| A-002 | [Specific action] | [Name] | [Date] | [How to verify success] | Improvement #2 |
| A-003 | [Specific action] | [Name] | [Date] | [How to verify success] | Improvement #3 |
Each action must be:
- Specific (not "improve estimation" but "add estimation review step to grooming")
- Owned (one person accountable)
- Time-bound (due date within next 1-2 sprints)
- Verifiable (success criteria defined)
Got: 2-4 improvement actions with owners and due dates.
If fail: If actions are too vague, apply the "how would you verify this was done?" test.
Step 5: Review Previous Actions and Write Report
Check previous retrospective actions for closure:
## Previous Action Review
| ID | Action | Owner | Status | Notes |
|----|--------|-------|--------|-------|
| A-prev-001 | [Action from last retro] | [Name] | Closed / Open / Recurring | [Outcome] |
| A-prev-002 | [Action from last retro] | [Name] | Closed / Open / Recurring | [Outcome] |
Flag recurring items (same issue appearing in 3+ retrospectives) — these need escalation or a different approach.
Write the complete retrospective:
# Retrospective: [Sprint N / Phase Name / Date Range]
## Date: [YYYY-MM-DD]
## Document ID: RETRO-[PROJECT]-[YYYY-MM-DD]
### Period Summary
- **Period**: [Sprint N / dates]
- **Planned**: [N items / N points]
- **Completed**: [N items / N points]
- **Velocity**: [N] (previous: [N])
- **Unplanned Work**: [N items]
### What Went Well
[From Step 2]
### What Needs Improvement
[From Step 3]
### Improvement Actions
[From Step 4]
### Previous Action Review
[From Step 5]
---
*Retrospective facilitated by: [Name/Agent]*
Save as RETRO-[YYYY-MM-DD].md.
Got: Complete retrospective document saved with actions, evidence, and previous action review.
If fail: If the retrospective has no improvement actions, it's not driving change — revisit Step 3.
Validation
- Retrospective file created with date-stamped filename
- Period summary includes quantitative metrics
- "What Went Well" has 3-5 evidence-backed items
- "What Needs Improvement" has 3-5 evidence-backed items
- Improvement actions have owners, due dates, and success criteria
- Previous retrospective actions reviewed for closure
- Recurring issues flagged
Pitfalls
- Blame game: Retrospectives review processes and practices, not people. Frame issues as systemic, not personal.
- Actions without follow-through: The biggest retrospective failure. Always review previous actions before creating new ones.
- Too many actions: 2-4 focused actions are better than 10 vague ones. The team can only absorb so many changes.
- No evidence: "We feel estimation is bad" is opinion. "3 of 5 items exceeded estimates by 50%" is data. Always attach evidence.
- Skipping the positives: Only discussing problems is demoralizing. Celebrating wins reinforces good practices.
Related Skills
generate-status-report— status reports provide the data for retrospectivesmanage-backlog— improvement actions feed back into the backlogplan-sprint— retrospective learnings improve sprint planning accuracydraft-project-charter— review charter assumptions and risk accuracycreate-work-breakdown-structure— review estimation accuracy against WBS
GitHub リポジトリ
関連スキル
content-collections
メタこのスキルは、Content Collections(Markdown/MDXファイルを型安全なデータコレクションに変換するTypeScriptファーストのツール)の本番環境でテストされた設定を提供します。Zodバリデーションによる型安全性を実現し、ブログ、ドキュメントサイト、コンテンツ重視のVite + Reactアプリケーション構築時にご利用ください。Viteプラグインの設定、MDXコンパイルから、デプロイ最適化、スキーマバリデーションまで、すべてを網羅しています。
polymarket
メタこのスキルは、開発者がPolymarket予測市場プラットフォームを活用したアプリケーション構築を可能にします。API統合による取引や市場データの取得に加え、WebSocketを介したリアルタイムデータストリーミングにより、ライブ取引や市場活動を監視できます。取引戦略の実装や、ライブ市場更新を処理するツールの作成にご利用ください。
creating-opencode-plugins
メタこのスキルは、開発者がコマンド、ファイル、LSP操作など25種類以上のイベントタイプにフックするOpenCodeプラグインを作成することを支援します。JavaScript/TypeScriptモジュール向けに、プラグイン構造、イベントAPI仕様、および実装パターンを提供します。カスタムイベント駆動ロジックでOpenCode AIアシスタントのライフサイクルをインターセプト、監視、または拡張する必要がある場合にご利用ください。
sglang
メタSGLangは、高性能なLLMサービングフレームワークであり、RadixAttentionプレフィックスキャッシュを活用したJSON、正規表現、エージェントワークフロー向けの高速で構造化された生成を特長とします。特にプレフィックスが繰り返されるタスクにおいて、大幅に高速な推論を実現し、複雑な構造化出力やマルチターン対話に最適です。制約付きデコードが必要な場合や、広範なプレフィックス共有を伴うアプリケーションを構築する場合は、vLLMなどの代替案ではなくSGLangを選択してください。