Plan Release Cycle
Plan structured software release cycle. Define strategy (calendar-based or feature-based). Set milestones with target dates. Establish feature freeze criteria. Manage release candidates. Define go/no-go checklists. Document rollback plans. Produces RELEASE-PLAN.md artifact guiding team from development through release.
When Use
- Starting planning for major or minor version release
- Transitioning from ad-hoc releases to structured release cadence
- Coordinating release across multiple teams or components
- Defining quality gates and release criteria for regulated project
- Planning first public release (v1.0.0) of a project
Inputs
- Required: Target version number (e.g. v2.0.0)
- Required: Desired release date or release window
- Required: List of planned features or scope (backlog, roadmap, description)
- Optional: Team size and availability
- Optional: Release strategy preference (calendar-based or feature-based)
- Optional: Regulatory or compliance requirements affecting release
- Optional: Previous release velocity or cycle duration data
Steps
Step 1: Determine Release Strategy
Pick between two main strategies:
Calendar-based (time-boxed):
- Release on fixed schedule (e.g. every 4 weeks, quarterly)
- Features not ready get deferred to next release
- Predictable for users and downstream projects
- Best for: libraries, frameworks, tools with external consumers
Feature-based (scope-driven):
- Release when defined set of features complete
- Date adjusts to fit scope
- Risk of scope creep and indefinite delays
- Best for: internal tools, first releases, major rewrites
For most projects, hybrid works well: set target date with defined scope. Allow 1-2 week buffer. Scope not met by buffer deadline? Defer remaining features.
Document strategy choice with reason.
Got: Release strategy documented with reason matching project context.
If fail: Team can't agree on strategy? Default to calendar-based with feature-priority list. Time-boxing forces prioritization decisions.
Step 2: Define Milestones
Break release cycle into phases with target dates:
## Release Plan: v2.0.0
### Timeline
| Phase | Start | End | Duration | Description |
|---|---|---|---|---|
| Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development |
| Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date |
| Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only |
| RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged |
| RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC |
| RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found |
| Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting |
| Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |
Typical phase durations:
- Development: 50-70% of total cycle
- Stabilization: 15-25% of total cycle
- RC testing: 10-20% of total cycle
Got: Milestone table with dates, durations, descriptions per phase.
If fail: Timeline too compressed (stabilization < 1 week)? Extend release date or reduce scope. NEVER skip stabilization.
Step 3: Set Feature Freeze Criteria
Define what "feature freeze" means for this release:
### Feature Freeze Criteria
After feature freeze (2026-03-15):
- **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches
- **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security)
- **Exception process**: Feature freeze exceptions require written justification and approval from [release owner]
### Feature Priority List
| Priority | Feature | Status | Owner | Notes |
|---|---|---|---|---|
| P0 (must) | New export format | In progress | [Name] | Blocks release |
| P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement |
| P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready |
| P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |
P0 features block release. P1 features included if ready. P2 features deferred without delay.
Got: Feature freeze rules documented with exception process and prioritized feature list.
If fail: P0 features at risk of missing freeze date? Escalate immediately. Options: extend development phase, split feature into smaller deliverable, defer to point release (v2.0.1).
Step 4: Plan Release Candidate Process
Define how release candidates produced and tested:
### Release Candidate Process
1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green
```bash
git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
-
RC Distribution: Publish RC to staging/testing channel
- R:
install.packages("pkg", repos = "https://staging.r-universe.dev/user") - Node.js:
npm install pkg@next - Internal: Deploy to staging environment
- R:
-
RC Testing Period: 5-7 business days
- Run full test suite including integration tests
- Verify all P0 features work as documented
- Test upgrade path from previous version
- Check for regressions in existing functionality
-
RC Evaluation:
- No critical/high bugs: Proceed to release
- Critical bugs found: Fix, tag RC2, restart testing period
- More than 2 RCs needed: Revisit scope and timeline
-
RC2+ Tags: Only if critical issues found in previous RC
git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
**Got:** RC process documented with tagging convention, distribution method, testing checklist, escalation criteria.
**If fail:** RC process skipped (pressure to release)? Document the risk. Untested releases have higher rollback probability.
### Step 5: Define Go/No-Go Checklist
Create criteria that must be met before release approval:
```markdown
### Go/No-Go Checklist
#### Must Pass (release blocked if any fail)
- [ ] All CI checks passing on release branch
- [ ] Zero critical bugs open against this version
- [ ] Zero high-severity security vulnerabilities
- [ ] All P0 features verified and documented
- [ ] Changelog complete and reviewed
- [ ] Upgrade path tested from previous version (v1.x -> v2.0.0)
- [ ] License and attribution files up to date
#### Should Pass (release proceeds with documented risk)
- [ ] Zero high bugs open (non-critical)
- [ ] All P1 features included
- [ ] Performance benchmarks within acceptable range
- [ ] Documentation reviewed and spell-checked
- [ ] External dependencies at latest stable versions
#### Decision
- **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked
- **No-Go**: Any "Must Pass" item unchecked
- **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks
Got: Go/no-go checklist with clear pass/fail criteria and decision rules.
If fail: Go/no-go meeting results in no-go? Identify blocking items, assign owners, set new target date (usually 1-2 weeks later), update release plan.
Step 6: Document Rollback Plan
Define how to roll back if release causes critical issues in production:
### Rollback Plan
#### Rollback Triggers
- Critical bug affecting >10% of users
- Data corruption or loss
- Security vulnerability introduced by the release
- Breaking change not documented in changelog
#### Rollback Procedure
1. **Revert package registry**: Unpublish or yank the release
- R/CRAN: Contact CRAN maintainers (cannot self-unpublish)
- npm: `npm unpublish [email protected]` (within 72 hours)
- GitHub: Mark release as pre-release, publish point fix
2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels
- Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released."
3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible
4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps
#### Point Release Policy
- v2.0.1 for critical bug fixes within 1 week of release
- v2.0.2 for additional fixes within 2 weeks
- Patch releases do not require full RC cycle but must pass CI and critical test suite
Write complete release plan to RELEASE-PLAN.md or RELEASE-PLAN-v2.0.0.md.
Got: Rollback plan documented with triggers, procedure, communication template, point release policy. Complete RELEASE-PLAN.md written.
If fail: Rollback not feasible (e.g. database migration already applied)? Document forward-fix procedure instead. Every release should have recovery path.
Checks
- Release strategy (calendar/feature/hybrid) documented with reason
- Milestone table includes all phases with dates: development, freeze, stabilization, RC, release
- Feature freeze criteria defined with allowed/disallowed change types
- Feature priority list categorized (P0 must / P1 should / P2 nice)
- RC process documented: tagging convention, distribution, testing period, escalation
- Go/no-go checklist has clear "must pass" and "should pass" sections
- Rollback plan includes triggers, procedure, communication template
- RELEASE-PLAN.md (or equivalent) file created and saved
- Timeline realistic (stabilization at least 15% of total cycle)
Pitfalls
- No stabilization phase: Going direct from development to release. Even 3-day stabilization catches issues active development masks.
- Scope creep after freeze: Allowing "just one more feature" after feature freeze. Every post-freeze addition resets testing and introduces regression risk.
- Ignore P0 risks: Not escalating early when P0 feature at risk. Earlier scope adjusted, less disruption to timeline.
- Skip RC for "small" releases: Even minor releases benefit from at least one RC. Day of RC testing cheaper than post-release hotfix.
- No rollback plan: Assuming release will succeed. Every release plan should answer "what if this goes wrong?" before publishing.
- Calendar pressure overriding quality: Releasing on date because promised, despite failing go/no-go criteria. Delayed release is minor inconvenience. Broken release is trust violation.
See Also
apply-semantic-versioning-- Determine version number for planned releasemanage-changelog-- Maintain changelog that feeds into release notesplan-sprint-- Sprint planning within development phase of release cycledraft-project-charter-- Project charter may define release roadmap and success criteriagenerate-status-report-- Track progress against release milestones
GitHub リポジトリ
関連スキル
executing-plans
デザインexecuting-plansスキルは、完全な実装計画があり、それを管理されたバッチでレビューチェックポイントを設けながら実行する場合に使用します。このスキルは計画を読み込んで批判的にレビューした後、小さなバッチ(デフォルトは3タスク)でタスクを実行し、各バッチの間に進捗状況を報告してアーキテクトのレビューを受けます。これにより、品質管理チェックポイントが組み込まれた体系的な実装が保証されます。
requesting-code-review
デザインこのスキルは、コードレビュアーサブエージェントを起動し、処理を進める前に要件に対してコード変更を分析します。タスク完了後、主要な機能の実装後、またはmainブランチへのマージ前などに使用すべきです。このレビューは、現在の実装と元の計画を比較することで、問題を早期に発見するのに役立ちます。
connect-mcp-server
デザインこのスキルは、開発者がHTTP、stdio、またはSSEトランスポートを使用してMCPサーバーをClaude Codeに接続するための包括的なガイドを提供します。GitHub、Notion、カスタムAPIなどの外部サービスを統合するためのインストール、設定、認証、セキュリティについて解説しています。MCP統合のセットアップ、外部ツールの設定、またはClaudeのModel Context Protocolを扱う際にご利用ください。
web-cli-teleport
デザインこのスキルは、タスク分析に基づいて開発者がClaude Code WebとCLIインターフェースの選択を支援し、これらの環境間でのシームレスなセッションテレポーテーションを可能にします。Web、CLI、モバイル環境を切り替える際のセッション状態とコンテキストを管理することで、ワークフローを最適化します。様々な段階で異なるツールを必要とする複雑なプロジェクトにご活用ください。