create-work-breakdown-structure

pjt222
업데이트됨 2 days ago
1 조회
17
2
17
GitHub에서 보기
메타data

정보

이 Claude Skill은 승인된 프로젝트 산출물로부터 상세한 작업 분할 구조(WBS)와 WBS 사전을 생성합니다. 계층적 분해, 노력 추정을 수행하며 의존성과 주요 경로 후보를 식별합니다. 고전적/폭포수식 프로젝트 계획 단계에서 이니셔티브를 추정 및 자원 할당이 가능한 관리형 작업 패키지로 분할할 때 사용하세요.

빠른 설치

Claude Code

추천
기본
npx skills add pjt222/agent-almanac -a claude-code
플러그인 명령대체
/plugin add https://github.com/pjt222/agent-almanac
Git 클론대체
git clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/create-work-breakdown-structure

Claude Code에서 이 명령을 복사하여 붙여넣어 스킬을 설치하세요

문서

Create a Work Breakdown Structure

Break project scope into hierarchical set of work packages. Estimable, assignable, trackable. WBS gives foundation for effort estimation, resource planning, schedule development. Breaks complex deliverables into manageable components.

When Use

  • After project charter approved and scope defined
  • Planning classic/waterfall project with defined deliverables
  • Breaking big initiative into manageable work packages
  • Setting basis for effort estimation and resource planning
  • Making shared understanding of all required work

Inputs

  • Required: Approved project charter (especially scope and deliverables sections)
  • Required: Project methodology (classic/waterfall, or hybrid with WBS for planning)
  • Optional: Historical effort data from similar projects
  • Optional: Team composition and available skills
  • Optional: Organizational WBS templates or standards

Steps

Step 1: Extract Deliverables from Charter

Read project charter. List all deliverables and acceptance criteria. Group into 3-7 top-level categories (these become WBS Level 1 elements).

Got: List of Level 1 WBS elements matching charter deliverables.

If fail: Charter vague? Return to draft-project-charter to refine scope.

Step 2: Decompose into Work Packages

For each Level 1 element, break into sub-elements (Level 2, Level 3). Apply 100% rule: child elements must represent 100% of parent's scope. Stop decomposing when work packages are:

  • Estimable (can assign effort in person-days)
  • Assignable (one person or team owns it)
  • Measurable (clear done/not-done criteria)

Create WBS outline:

# Work Breakdown Structure: [Project Name]
## Document ID: WBS-[PROJECT]-[YYYY]-[NNN]

### WBS Hierarchy

1. [Level 1: Deliverable Category A]
   1.1 [Level 2: Sub-deliverable]
      1.1.1 [Level 3: Work Package]
      1.1.2 [Level 3: Work Package]
   1.2 [Level 2: Sub-deliverable]
2. [Level 1: Deliverable Category B]
   2.1 [Level 2: Sub-deliverable]
3. [Level 1: Project Management]
   3.1 Planning
   3.2 Monitoring & Control
   3.3 Closure

Apply WBS codes (1.1.1 format). Keep 3-5 levels deep max. Always include "Project Management" branch.

Got: Complete WBS with 15-50 work packages, each with unique WBS code.

If fail: Decomposition exceeds 5 levels? Scope too large — consider splitting into sub-projects.

Step 3: Write WBS Dictionary

For each work package (leaf node), write dictionary entry:

# WBS Dictionary: [Project Name]
## Document ID: WBS-DICT-[PROJECT]-[YYYY]-[NNN]

### WBS 1.1.1: [Work Package Name]
- **Description**: What this work package produces
- **Acceptance Criteria**: How to verify it's done
- **Responsible**: Person or role
- **Estimated Effort**: [T-shirt size or person-days]
- **Dependencies**: WBS codes this depends on
- **Assumptions**: Key assumptions for this work package

### WBS 1.1.2: [Work Package Name]
...

Got: Dictionary entry for every leaf-node work package.

If fail: Missing dictionary entries → incomplete decomposition. Revisit Step 2.

Step 4: Estimate Effort

For each work package, apply one estimation method:

  • T-shirt sizing (XS/S/M/L/XL) for early-stage planning
  • Person-days for detailed planning
  • Three-point estimate (optimistic/most likely/pessimistic) for high-uncertainty work

Create summary table:

## Effort Summary
| WBS Code | Work Package | Estimate | Method | Confidence |
|----------|-------------|----------|--------|------------|
| 1.1.1 | [Name] | 5 pd | person-days | High |
| 1.1.2 | [Name] | M | t-shirt | Medium |

Total effort = sum of all work packages.

Got: Every work package has effort estimate with stated confidence.

If fail: Confidence Low on >30% of packages? Schedule refinement session with SMEs.

Step 5: Identify Dependencies and Critical Path Candidates

Map dependencies between work packages:

## Dependencies
| WBS Code | Depends On | Type | Notes |
|----------|-----------|------|-------|
| 1.2.1 | 1.1.1 | Finish-to-Start | Output of 1.1.1 is input to 1.2.1 |
| 2.1.1 | 1.1.2 | Finish-to-Start | |

Find longest chain of dependent work packages — this is critical path candidate.

Got: Dependency table with at least finish-to-start relationships identified.

If fail: Dependencies form cycles? Decomposition has errors. Revisit Step 2.

Step 6: Review and Baseline

Combine WBS and dictionary into final documents. Verify 100% rule at every level. Get stakeholder sign-off.

Got: WBS.md and WBS-DICTIONARY.md files created and reviewed.

If fail: Stakeholders identify missing scope? Add work packages and re-estimate.

Checks

  • WBS file created with document ID and WBS codes
  • 100% rule satisfied: children fully represent parent scope at every level
  • Every leaf node has WBS dictionary entry
  • All work packages have effort estimates
  • Dependencies identified with no circular references
  • Project Management branch included
  • Critical path candidates identified
  • WBS depth does not exceed 5 levels

Pitfalls

  • Confusing deliverables with activities: WBS elements should be nouns (deliverables), not verbs (activities). "User Authentication Module" not "Implement Authentication".
  • Violating the 100% rule: Children don't add up to 100% of parent scope → work will be missed.
  • Too shallow or too deep: 2 levels too vague for planning; 6+ levels is micromanagement. Target 3-5 levels.
  • Skipping Project Management branch: PM work (planning, meetings, reporting) is real work consuming effort.
  • Estimating before decomposing: Estimate work packages, not categories. Level 1 estimate unreliable.
  • No dictionary: WBS without dictionary is tree of labels. Dictionary gives definition of done.

See Also

  • draft-project-charter — gives scope and deliverables feeding WBS decomposition
  • manage-backlog — translate WBS work packages into backlog items for tracking
  • generate-status-report — report progress against WBS % complete
  • plan-sprint — if using hybrid approach, sprint-plan from WBS work packages
  • conduct-retrospective — review estimation accuracy and decomposition quality

GitHub 저장소

pjt222/agent-almanac
경로: i18n/caveman/skills/create-work-breakdown-structure
0
agentsagentskillsai-assisted-developmentclaude-codeskillsteams

연관 스킬

content-collections

메타

이 스킬은 콘텐츠 콜렉션(Content Collections)을 위한 프로덕션 검증된 설정을 제공합니다. 콘텐츠 콜렉션은 Markdown/MDX 파일을 Zod 검증이 포함된 타입 안전한 데이터 콜렉션으로 변환해주는 TypeScript 최우선 도구입니다. 블로그, 문서 사이트 또는 콘텐츠 중심의 Vite + React 애플리케이션을 구축할 때 타입 안전성과 자동 콘텐츠 검증을 보장하기 위해 사용하세요. Vite 플러그인 구성과 MDX 컴파일부터 배포 최적화 및 스키마 검증에 이르기까지 모든 것을 다룹니다.

스킬 보기

polymarket

메타

이 스킬은 개발자들이 Polymarket 예측 시장 플랫폼을 활용한 애플리케이션을 구축할 수 있도록 지원하며, 거래 및 시장 데이터를 위한 API 통합 기능을 포함합니다. 또한 WebSocket을 통한 실시간 데이터 스트리밍을 제공하여 실시간 거래와 시장 활동을 모니터링할 수 있습니다. 이를 통해 거래 전략을 구현하거나 실시간 시장 업데이트를 처리하는 도구를 생성하는 데 활용할 수 있습니다.

스킬 보기

creating-opencode-plugins

메타

이 스킬은 개발자들이 명령어, 파일, LSP 작업 등 25개 이상의 이벤트 유형에 연결되는 OpenCode 플러그인을 만들 수 있도록 돕습니다. JavaScript/TypeScript 모듈을 위한 플러그인 구조, 이벤트 API 명세, 구현 패턴을 제공합니다. OpenCode AI 어시스턴트의 라이프사이클을 사용자 정의 이벤트 기반 로직으로 가로채거나, 모니터링하거나, 확장해야 할 때 사용하세요.

스킬 보기

sglang

메타

SGLang은 RadixAttention 프리픽스 캐싱을 활용하여 JSON, 정규식, 에이전트 워크플로우를 위한 고속 구조화 생성에 특화된 고성능 LLM 서빙 프레임워크입니다. 특히 반복되는 프리픽스가 있는 작업에서 상당히 빠른 추론 속도를 제공하여 복잡한 구조화 출력 및 다중 턴 대화에 이상적입니다. 제약 디코딩이 필요하거나 광범위한 프리픽스 공유가 있는 애플리케이션을 구축할 때는 vLLM과 같은 대안보다 SGLang을 선택하십시오.

스킬 보기