Generate a Project Status Report
Periodic status: read artifacts → metrics → summary (accomplishments, blockers, next) → RAG health (sched/scope/budget/quality).
Use When
- End of sprint/period (wk/bi-wk/mo)
- Stakeholder health req
- Pre steering/governance meeting
- Health change (new blocker/risk)
- Checkpoint vs charter milestones
In
- Required: period (start, end)
- Required: ≥1 artifact (BACKLOG.md, SPRINT-PLAN.md, WBS.md, PROJECT-CHARTER.md)
- Optional: prior reports (trend)
- Optional: budget/resource data
- Optional: risk register updates
Do
Step 1: Read artifacts
Scan proj dir:
- PROJECT-CHARTER.md — milestones, success criteria
- BACKLOG.md — item counts, burn-down
- SPRINT-PLAN.md — goal, committed, task done
- WBS.md — work pkg %
- Prior STATUS-REPORT-*.md — trend
Adapt to what exists.
→ ≥1 read, key metrics extracted.
If err: no artifacts → can't generate. Create charter/backlog first via draft-project-charter or manage-backlog.
Step 2: Metrics
Agile (BACKLOG.md / SPRINT-PLAN.md):
- Velocity: pts this sprint
- Completion: done/committed
- Burn-down: remaining vs prev
- Cycle time: avg days In Progress → Done
Classic (WBS.md):
- % complete: pkgs done / total
- Schedule variance: planned vs actual
- Effort variance: est vs consumed
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
→ 3-5 metrics w/ prev comparison.
If err: no historical (first) → omit prev + trend cols. Incomplete → note gaps + track action items.
Step 3: Blockers, risks, issues
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
Cross-ref charter risk register. Flag new.
→ All blockers + top risks w/ owners + actions.
If err: no blockers → explicit "No active blockers", don't leave empty. No owner → escalate to PM.
Step 4: Accomplishments + next plan
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
→ 3-5 accomplishments w/ evidence, 3-5 planned.
If err: no accomplishments → reason (blocked, replanning, unavail). Next unclear → "Planning session scheduled for [date]".
Step 5: RAG + write
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
Write:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
Save STATUS-REPORT-[YYYY-MM-DD].md.
→ Complete report w/ RAG + metrics + narrative.
If err: insufficient for RAG → ⚪ (Grey) "insufficient data" + list data needed next report.
Check
- Report file created, date-stamped
- RAG all 4 dims w/ justify
- ≥3 metrics from artifacts
- Blockers section present (even "No active")
- Accomplishments w/ evidence
- Next plan
- Exec summary 2-3 sentences
- Every blocker/risk has owner + action + deadline
Traps
- No data: evidence-based. Every claim → artifact/metric.
- All green always: no evidence = not honest. Challenge green.
- Blocker w/o owner: no owner → not resolved.
- Metric w/o context: "Velocity=18" meaningless alone. Always prev/target.
- Too long: 2 min scan. 1-2 pages.
- Missing decisions: explicit w/ deadlines.
- Stale data: verify artifact dates match period.
- Missing trends: first-time OK, later must compare.
→
draft-project-charter— milestones + success criteriamanage-backlog— backlog metrics feed reportplan-sprint— sprint results: velocity + completioncreate-work-breakdown-structure— WBS % drives classic metricsconduct-retrospective— report data feeds retro
GitHub 저장소
연관 스킬
content-collections
메타이 스킬은 콘텐츠 콜렉션(Content Collections)을 위한 프로덕션 검증된 설정을 제공합니다. 콘텐츠 콜렉션은 Markdown/MDX 파일을 Zod 검증이 포함된 타입 안전한 데이터 콜렉션으로 변환해주는 TypeScript 최우선 도구입니다. 블로그, 문서 사이트 또는 콘텐츠 중심의 Vite + React 애플리케이션을 구축할 때 타입 안전성과 자동 콘텐츠 검증을 보장하기 위해 사용하세요. Vite 플러그인 구성과 MDX 컴파일부터 배포 최적화 및 스키마 검증에 이르기까지 모든 것을 다룹니다.
polymarket
메타이 스킬은 개발자들이 Polymarket 예측 시장 플랫폼을 활용한 애플리케이션을 구축할 수 있도록 지원하며, 거래 및 시장 데이터를 위한 API 통합 기능을 포함합니다. 또한 WebSocket을 통한 실시간 데이터 스트리밍을 제공하여 실시간 거래와 시장 활동을 모니터링할 수 있습니다. 이를 통해 거래 전략을 구현하거나 실시간 시장 업데이트를 처리하는 도구를 생성하는 데 활용할 수 있습니다.
creating-opencode-plugins
메타이 스킬은 개발자들이 명령어, 파일, LSP 작업 등 25개 이상의 이벤트 유형에 연결되는 OpenCode 플러그인을 만들 수 있도록 돕습니다. JavaScript/TypeScript 모듈을 위한 플러그인 구조, 이벤트 API 명세, 구현 패턴을 제공합니다. OpenCode AI 어시스턴트의 라이프사이클을 사용자 정의 이벤트 기반 로직으로 가로채거나, 모니터링하거나, 확장해야 할 때 사용하세요.
sglang
메타SGLang은 RadixAttention 프리픽스 캐싱을 활용하여 JSON, 정규식, 에이전트 워크플로우를 위한 고속 구조화 생성에 특화된 고성능 LLM 서빙 프레임워크입니다. 특히 반복되는 프리픽스가 있는 작업에서 상당히 빠른 추론 속도를 제공하여 복잡한 구조화 출력 및 다중 턴 대화에 이상적입니다. 제약 디코딩이 필요하거나 광범위한 프리픽스 공유가 있는 애플리케이션을 구축할 때는 vLLM과 같은 대안보다 SGLang을 선택하십시오.