Dependency Tracking

Overview

Dependency tracking ensures visibility of task relationships, identifies blocking issues early, and enables better resource planning and risk mitigation.

When to Use

  • Multi-team projects and programs
  • Complex technical integrations
  • Cross-organizational initiatives
  • Identifying critical path items
  • Resource allocation planning
  • Preventing schedule delays
  • Onboarding new team members

Instructions

1. Dependency Mapping

# Dependency mapping and tracking

class DependencyTracker:
    DEPENDENCY_TYPES = {
        'Finish-to-Start': 'Task B cannot start until Task A is complete',
        'Start-to-Start': 'Task B cannot start until Task A starts',
        'Finish-to-Finish': 'Task B cannot finish until Task A is complete',
        'Start-to-Finish': 'Task B cannot finish until Task A starts'
    }

    def __init__(self):
        self.tasks = []
        self.dependencies = []
        self.critical_path = []

    def create_dependency_map(self, tasks):
        """Create visual dependency network"""
        dependency_graph = {
            'nodes': [],
            'edges': [],
            'critical_items': []
        }

        for task in tasks:
            dependency_graph['nodes'].append({
                'id': task.id,
                'name': task.name,
                'duration': task.duration,
                'owner': task.owner,
                'status': task.status
            })

            for blocker in task.blocked_by:
                dependency_graph['edges'].append({
                    'from': blocker,
                    'to': task.id,
                    'type': 'Finish-to-Start',
                    'lag': 0  # days between tasks
                })

        return dependency_graph

    def analyze_critical_path(self, tasks):
        """Identify longest chain of dependent tasks"""
        paths = self.find_all_paths(tasks)
        critical_path = max(paths, key=len)

        return {
            'critical_items': critical_path,
            'total_duration': sum(t.duration for t in critical_path),
            'slack_available': 0,
            'any_delay_impacts_schedule': True,
            'monitoring_frequency': 'Daily'
        }

    def identify_blocking_dependencies(self, tasks):
        """Find tasks that block other work"""
        blocking_tasks = {}

        for task in tasks:
            blocked_count = sum(1 for t in tasks if task.id in t.blocked_by)
            if blocked_count > 0:
                blocking_tasks[task.id] = {
                    'task': task.name,
                    'blocking_count': blocked_count,
                    'blocked_tasks': [t.id for t in tasks if task.id in t.blocked_by],
                    'status': task.status,
                    'due_date': task.due_date,
                    'risk_level': 'High' if blocked_count > 3 else 'Medium'
                }

        return blocking_tasks

    def find_circular_dependencies(self, tasks):
        """Detect circular dependency chains"""
        cycles = []

        for task in tasks:
            visited = set()
            if self.has_cycle(task, visited, tasks):
                cycles.append({
                    'cycle': visited,
                    'severity': 'Critical',
                    'action': 'Resolve immediately'
                })

        return cycles

    def has_cycle(self, task, visited, tasks):
        visited.add(task.id)

        for blocker_id in task.blocked_by:
            blocker = next(t for t in tasks if t.id == blocker_id)

            if blocker.id in visited:
                return True
            if self.has_cycle(blocker, visited, tasks):
                return True

        visited.remove(task.id)
        return False

2. Dependency Management Board

Dependency Tracking Dashboard:

Project: Platform Migration Q1 2025

---

Critical Path (Blocking Progress):

Task: Database Migration
  ID: TASK-101
  Owner: Data Team
  Duration: 20 days
  Status: In Progress (50%)
  Due Date: Feb 28, 2025
  Blocked By: Schema validation (TASK-95) - DUE TODAY
  Blocks: 6 downstream tasks
  Risk Level: HIGH
  Action Items:
    - Daily standup with Data Team
    - Schema validation must complete by EOD
    - Have rollback plan ready

---

Task: API Contract Finalization
  ID: TASK-102
  Owner: Backend Team
  Duration: 10 days
  Status: Pending (Blocked)
  Depends On: Database Migration (TASK-101)
  Blocks: Frontend implementation (TASK-103), Testing (TASK-104)
  Slack Time: 0 days (critical)
  Early Start: Mar 1, 2025
  Action Items:
    - Start draft specifications now
    - Review with Frontend team
    - Have alternative approach ready

---

High-Risk Dependencies:

Dependency: Third-party Integration
  From: Payment Service API (vendor)
  To: Checkout System (TASK-150)
  Type: External/Uncontrollable
  Status: At Risk (Vendor delay reported)
  Mitigation: Mock service implementation, alternative vendor identified
  Escalation Owner: Product Manager

---

By Team Dependencies:

Backend Team:
  - Database migration → API development
  - Schema design → Data layer implementation
  External: Awaiting Payment Gateway API docs

Frontend Team:
  - API contracts → UI implementation
  - Design system → Component development
  Dependency on Backend: API contract specs (scheduled Feb 20)

DevOps Team:
  - Infrastructure provisioning → Testing environment
  - Kubernetes setup → Staging deployment
  External: Cloud provider quota approval

3. Dependency Resolution

// Handling and resolving dependency issues

class DependencyResolution {
  resolveDependencyConflict(blocker, blocked) {
    return {
      conflict: {
        blocking_task: blocker.name,
        blocked_task: blocked.name,
        reason: 'Circular dependency detected'
      },
      resolution_options: [
        {
          option: 'Parallelize Work',
          description: 'Identify independent portions that can proceed',
          effort: 'Medium',
          timeline: 'Can save 5 days'
        },
        {
          option: 'Remove/Defer Blocker',
          description: 'Defer non-critical requirements',
          effort: 'Low',
          timeline: 'Immediate'
        },
        {
          option: 'Create Interim Deliverable',
          description: 'Deliver partial results to unblock downstream',
          effort: 'High',
          timeline: 'Can save 8 days'
        }
      ]
    };
  }

  breakDependency(dependency) {
    return {
      current_state: dependency,
      break_strategies: [
        {
          strategy: 'Remove unnecessary dependency',
          action: 'Refactor to eliminate requirement',
          risk: 'Low if verified'
        },
        {
          strategy: 'Mock/Stub external dependency',
          action: 'Create temporary implementation',
          risk: 'Medium - ensures compatibility'
        },
        {
          strategy: 'Parallel development',
          action: 'Make assumptions, validate later',
          risk: 'Medium - rework possible'
        },
        {
          strategy: 'Resource addition',
          action: 'Parallelize work streams',
          risk: 'Low but costly'
        }
      ]
    };
  }

  handleBlockedTask(task) {
    return {
      task_id: task.id,
      status: 'Blocked',
      blocker: task.blocked_by[0],
      time_blocked: task.calculateBlockedDuration(),
      actions: [
        'Notify team of blockage',
        'Escalate if critical path',
        'Identify alternative work',
        'Schedule resolution meeting',
        'Track blocker closure date'
      ],
      escalation: {
        immediate: task.is_critical_path,
        owner: task.program_manager,
        frequency: 'Daily standup until resolved'
      }
    };
  }
}

4. Dependency Dashboard Metrics

Key Metrics:

Critical Path Health:
  - Items on Critical Path: 12
  - At-Risk Items: 2 (17%)
  - Completed: 4 (33%)
  - On Track: 6 (50%)
  - Behind: 2 (17%)

Dependency Status:
  - Total Dependencies: 28
  - Resolved: 18
  - Active: 8
  - At Risk: 2
  - Circular: 0 (Good!)

Blocking Impact:
  - Tasks Currently Blocked: 3
  - Team Members Idle: 2
  - Blocked Effort (person-hours): 24
  - Estimated Cost of Blockage: $2,400

Escalations:
  - Open: 1 (Database migration dependency)
  - Resolved This Week: 0
  - Average Resolution Time: 2.3 days

Best Practices

✅ DO

  • Map dependencies early in planning
  • Update dependency tracking weekly
  • Identify and monitor critical path items
  • Proactively communicate blockers
  • Have contingency plans for key dependencies
  • Break complex dependencies into smaller pieces
  • Track external dependencies separately
  • Escalate blocked critical path items immediately
  • Remove unnecessary dependencies
  • Build in buffer time for risky dependencies

❌ DON'T

  • Ignore external dependencies
  • Leave circular dependencies unresolved
  • Assume dependencies will "work out"
  • Skip daily monitoring of critical path
  • Communicate issues only in status meetings
  • Create too many dependencies (couples systems)
  • Forget to document dependency rationale
  • Avoid escalating blocked critical work
  • Plan at 100% utilization (no buffer for dependencies)
  • Treat all dependencies as equal priority

Dependency Management Tips

  • Color-code by risk level in tracking tools
  • Weekly review of blocked/at-risk items
  • Maintain updated dependency diagram
  • Escalate after 1 day of blockage on critical path
  • Build 15-20% buffer for risky dependencies

Quick Install

/plugin add https://github.com/aj-geddes/useful-ai-prompts/tree/main/dependency-tracking

Copy and paste this command in Claude Code to install this skill

GitHub 仓库

aj-geddes/useful-ai-prompts
Path: skills/dependency-tracking

Related Skills

subagent-driven-development

Development

This skill executes implementation plans by dispatching a fresh subagent for each independent task, with code review between tasks. It enables fast iteration while maintaining quality gates through this review process. Use it when working on mostly independent tasks within the same session to ensure continuous progress with built-in quality checks.

View skill

algorithmic-art

Meta

This Claude Skill creates original algorithmic art using p5.js with seeded randomness and interactive parameters. It generates .md files for algorithmic philosophies, plus .html and .js files for interactive generative art implementations. Use it when developers need to create flow fields, particle systems, or other computational art while avoiding copyright issues.

View skill

executing-plans

Design

Use the executing-plans skill when you have a complete implementation plan to execute in controlled batches with review checkpoints. It loads and critically reviews the plan, then executes tasks in small batches (default 3 tasks) while reporting progress between each batch for architect review. This ensures systematic implementation with built-in quality control checkpoints.

View skill

cost-optimization

Other

This Claude Skill helps developers optimize cloud costs through resource rightsizing, tagging strategies, and spending analysis. It provides a framework for reducing cloud expenses and implementing cost governance across AWS, Azure, and GCP. Use it when you need to analyze infrastructure costs, right-size resources, or meet budget constraints.