This Claude Skill creates a detailed Work Breakdown Structure (WBS) and WBS Dictionary from approved project deliverables. It performs hierarchical decomposition, effort estimation, and identifies dependencies and critical path candidates. Use it during classic/waterfall project planning to break down initiatives into manageable work packages for estimation and resource allocation.
快速安装
Claude Code
推荐npx skills add pjt222/agent-almanac -a claude-code/plugin add https://github.com/pjt222/agent-almanacgit clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/create-work-breakdown-structure在 Claude Code 中复制并粘贴此命令以安装该技能
技能文档
Create a Work Breakdown Structure
Break project scope into hierarchical set of work packages. Estimable, assignable, trackable. WBS gives foundation for effort estimation, resource planning, schedule development. Breaks complex deliverables into manageable components.
When Use
- After project charter approved and scope defined
- Planning classic/waterfall project with defined deliverables
- Breaking big initiative into manageable work packages
- Setting basis for effort estimation and resource planning
- Making shared understanding of all required work
Inputs
- Required: Approved project charter (especially scope and deliverables sections)
- Required: Project methodology (classic/waterfall, or hybrid with WBS for planning)
- Optional: Historical effort data from similar projects
- Optional: Team composition and available skills
- Optional: Organizational WBS templates or standards
Steps
Step 1: Extract Deliverables from Charter
Read project charter. List all deliverables and acceptance criteria. Group into 3-7 top-level categories (these become WBS Level 1 elements).
Got: List of Level 1 WBS elements matching charter deliverables.
If fail: Charter vague? Return to draft-project-charter to refine scope.
Step 2: Decompose into Work Packages
For each Level 1 element, break into sub-elements (Level 2, Level 3). Apply 100% rule: child elements must represent 100% of parent's scope. Stop decomposing when work packages are:
- Estimable (can assign effort in person-days)
- Assignable (one person or team owns it)
- Measurable (clear done/not-done criteria)
Create WBS outline:
# Work Breakdown Structure: [Project Name]
## Document ID: WBS-[PROJECT]-[YYYY]-[NNN]
### WBS Hierarchy
1. [Level 1: Deliverable Category A]
1.1 [Level 2: Sub-deliverable]
1.1.1 [Level 3: Work Package]
1.1.2 [Level 3: Work Package]
1.2 [Level 2: Sub-deliverable]
2. [Level 1: Deliverable Category B]
2.1 [Level 2: Sub-deliverable]
3. [Level 1: Project Management]
3.1 Planning
3.2 Monitoring & Control
3.3 Closure
Apply WBS codes (1.1.1 format). Keep 3-5 levels deep max. Always include "Project Management" branch.
Got: Complete WBS with 15-50 work packages, each with unique WBS code.
If fail: Decomposition exceeds 5 levels? Scope too large — consider splitting into sub-projects.
Step 3: Write WBS Dictionary
For each work package (leaf node), write dictionary entry:
# WBS Dictionary: [Project Name]
## Document ID: WBS-DICT-[PROJECT]-[YYYY]-[NNN]
### WBS 1.1.1: [Work Package Name]
- **Description**: What this work package produces
- **Acceptance Criteria**: How to verify it's done
- **Responsible**: Person or role
- **Estimated Effort**: [T-shirt size or person-days]
- **Dependencies**: WBS codes this depends on
- **Assumptions**: Key assumptions for this work package
### WBS 1.1.2: [Work Package Name]
...
Got: Dictionary entry for every leaf-node work package.
If fail: Missing dictionary entries → incomplete decomposition. Revisit Step 2.
Step 4: Estimate Effort
For each work package, apply one estimation method:
- T-shirt sizing (XS/S/M/L/XL) for early-stage planning
- Person-days for detailed planning
- Three-point estimate (optimistic/most likely/pessimistic) for high-uncertainty work
Create summary table:
## Effort Summary
| WBS Code | Work Package | Estimate | Method | Confidence |
|----------|-------------|----------|--------|------------|
| 1.1.1 | [Name] | 5 pd | person-days | High |
| 1.1.2 | [Name] | M | t-shirt | Medium |
Total effort = sum of all work packages.
Got: Every work package has effort estimate with stated confidence.
If fail: Confidence Low on >30% of packages? Schedule refinement session with SMEs.
Step 5: Identify Dependencies and Critical Path Candidates
Map dependencies between work packages:
## Dependencies
| WBS Code | Depends On | Type | Notes |
|----------|-----------|------|-------|
| 1.2.1 | 1.1.1 | Finish-to-Start | Output of 1.1.1 is input to 1.2.1 |
| 2.1.1 | 1.1.2 | Finish-to-Start | |
Find longest chain of dependent work packages — this is critical path candidate.
Got: Dependency table with at least finish-to-start relationships identified.
If fail: Dependencies form cycles? Decomposition has errors. Revisit Step 2.
Step 6: Review and Baseline
Combine WBS and dictionary into final documents. Verify 100% rule at every level. Get stakeholder sign-off.
Got: WBS.md and WBS-DICTIONARY.md files created and reviewed.
If fail: Stakeholders identify missing scope? Add work packages and re-estimate.
Checks
- WBS file created with document ID and WBS codes
- 100% rule satisfied: children fully represent parent scope at every level
- Every leaf node has WBS dictionary entry
- All work packages have effort estimates
- Dependencies identified with no circular references
- Project Management branch included
- Critical path candidates identified
- WBS depth does not exceed 5 levels
Pitfalls
- Confusing deliverables with activities: WBS elements should be nouns (deliverables), not verbs (activities). "User Authentication Module" not "Implement Authentication".
- Violating the 100% rule: Children don't add up to 100% of parent scope → work will be missed.
- Too shallow or too deep: 2 levels too vague for planning; 6+ levels is micromanagement. Target 3-5 levels.
- Skipping Project Management branch: PM work (planning, meetings, reporting) is real work consuming effort.
- Estimating before decomposing: Estimate work packages, not categories. Level 1 estimate unreliable.
- No dictionary: WBS without dictionary is tree of labels. Dictionary gives definition of done.
See Also
draft-project-charter— gives scope and deliverables feeding WBS decompositionmanage-backlog— translate WBS work packages into backlog items for trackinggenerate-status-report— report progress against WBS % completeplan-sprint— if using hybrid approach, sprint-plan from WBS work packagesconduct-retrospective— review estimation accuracy and decomposition quality
GitHub 仓库
相关推荐技能
content-collections
元Content Collections 是一个 TypeScript 优先的构建工具,可将本地 Markdown/MDX 文件转换为类型安全的数据集合。它专为构建博客、文档站和内容密集型 Vite+React 应用而设计,提供基于 Zod 的自动模式验证。该工具涵盖从 Vite 插件配置、MDX 编译到生产环境部署的完整工作流。
polymarket
元这个Claude Skill为开发者提供完整的Polymarket预测市场开发支持,涵盖API调用、交易执行和市场数据分析。关键特性包括实时WebSocket数据流,可监控实时交易、订单和市场动态。开发者可用它构建预测市场应用、实施交易策略并集成实时市场预测功能。
creating-opencode-plugins
元该Skill帮助开发者创建OpenCode插件,用于接入命令、文件、LSP等25+种事件。它提供了插件结构、事件API规范和JavaScript/TypeScript实现模式,适合需要拦截操作、扩展功能或自定义事件处理的场景。开发者可通过它快速构建响应式模块来增强OpenCode AI助手的能力。
sglang
元SGLang是一个专为LLM设计的高性能推理框架,特别适用于需要结构化输出的场景。它通过RadixAttention前缀缓存技术,在处理JSON、正则表达式、工具调用等具有重复前缀的复杂工作流时,能实现极速生成。如果你正在构建智能体或多轮对话系统,并追求远超vLLM的推理性能,SGLang是理想选择。