generate-status-report
关于
This skill automatically generates a project status report by analyzing existing project artifacts like charters and backlogs. It calculates metrics, identifies blockers, and summarizes progress using RAG (Red/Amber/Green) indicators for schedule, scope, budget, and quality. Use it at the end of a sprint, before governance meetings, or when stakeholders request a health update.
快速安装
Claude Code
推荐npx skills add pjt222/agent-almanac -a claude-code/plugin add https://github.com/pjt222/agent-almanacgit clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/generate-status-report在 Claude Code 中复制并粘贴此命令以安装该技能
技能文档
項目狀況報告之生
析項目成品、算進度、摘成就阻滯與後續、以 RAG(紅/琥/綠)健康指示生週期狀況報告。
用時
- 衝刺或報告期末(週、雙週、月)
- 利益相關者求項目健康更新
- 前指導委員會或治理會議
- 項目健康指標變(如新阻滯或風險現)
- 相對章程里程之週期察
入
- 必要:報告期(始、終日)
- 必要:至少一項目成品(BACKLOG.md、SPRINT-PLAN.md、WBS.md 或 PROJECT-CHARTER.md)
- 可選:前狀況報告(為趨勢比較)
- 可選:預算或資源跟蹤資料
- 可選:風險登記更新
法
第一步:讀現有成品
掃項目目錄察 PM 成品:
- PROJECT-CHARTER.md — 里程、成功準則
- BACKLOG.md — 按狀態計項、燃盡資料
- SPRINT-PLAN.md — 衝刺目標、承諾項、任務完成
- WBS.md — 工作包完成百分比
- 前 STATUS-REPORT-*.md 檔 — 趨勢資料
讀可得檔。非必皆存——報告依可得資料適應。
得: 至少一成品成功讀取,要指標已抽。
敗則: 無成品則無法生報告。先以 draft-project-charter 或 manage-backlog 技能創章程或待辦。
第二步:算進度指標
自可得資料算指標:
敏捷指標(BACKLOG.md / SPRINT-PLAN.md):
- 速度:本衝刺完成之故事點
- 衝刺完成:完成項 / 承諾項
- 待辦燃盡:剩餘點對比前期
- 週期時:平均從進行中至完成之日數
經典指標(WBS.md):
- 完成率:完成工作包 / 總工作包
- 進度差異:計劃里程日 vs 實際
- 工作量差異:估計工作量 vs 實耗
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
得: 三至五指標已算,與前期比。
敗則: 若無歷史資料(首報),略 Previous 與 Trend 列。若資料不全,於報告腳注標間隙,附行動項以立跟蹤。
第三步:識阻滯、風險、問題
列活動阻滯與風險:
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
交叉比對章程風險登記。標任何前未識之新風險。
得: 所有活動阻滯與頂風險皆記,附擁者與行動。
敗則: 若無阻滯,顯陳「無活動阻滯」——勿留空。阻滯無擁者則升至項目經理指派。
第四步:摘成就與下期計劃
書二節:
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
得: 三至五成就附具體證據,下期三至五計劃項。
敗則: 若無成就,報原因(受阻、重劃、隊不可得)。若下期計劃不明,列「計劃會排於 [日]」為主項。
第五步:賦 RAG 指示並書報告
四維度察項目健康:
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
書完整報告:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
存為 STATUS-REPORT-[YYYY-MM-DD].md。
得: 完整狀況報告存,含 RAG 指示、指標、敘述。
敗則: 若資料不足為 RAG 評估,用 ⚪(灰)示「資料不足」,列下期須收集之資料。
驗
- 狀況報告檔創有正日戳檔名
- 四維度皆賦 RAG 指示有理由
- 自項目成品算至少三指標
- 阻滯節存(即使「無活動阻滯」)
- 成就有證據列出
- 下期計劃含入
- 執行摘要二至三句,非段
- 每阻滯與風險有擁者與行動與期限
陷
- 報告無資料:狀況報告必有據。每聲明皆應參成品或指標
- 恆綠不怠:持綠 RAG 無據示報告不誠。挑戰綠評
- 阻滯無擁者:每阻滯需擁者與行動。無擁阻滯不解
- 指標無語境:「速度 = 18」無比較無義。必含前期或目標
- 過長:狀況報告應二分鐘可掃。保一至二頁
- 缺決策節:若項目需利益相關者決策,顯陳附期限
- 資料陳舊:用舊成品致誤報。驗成品日合報告期
- 缺趨勢資料:首報不能顯趨勢,然後續報必比前期
參
draft-project-charter— 章程供狀況跟蹤之里程與成功準則manage-backlog— 待辦指標入狀況報告plan-sprint— 衝刺結果供速度與完成資料create-work-breakdown-structure— WBS 完成驅動經典進度指標conduct-retrospective— 狀況報告資料入回顧
GitHub 仓库
相关推荐技能
content-collections
元Content Collections 是一个 TypeScript 优先的构建工具,可将本地 Markdown/MDX 文件转换为类型安全的数据集合。它专为构建博客、文档站和内容密集型 Vite+React 应用而设计,提供基于 Zod 的自动模式验证。该工具涵盖从 Vite 插件配置、MDX 编译到生产环境部署的完整工作流。
polymarket
元这个Claude Skill为开发者提供完整的Polymarket预测市场开发支持,涵盖API调用、交易执行和市场数据分析。关键特性包括实时WebSocket数据流,可监控实时交易、订单和市场动态。开发者可用它构建预测市场应用、实施交易策略并集成实时市场预测功能。
creating-opencode-plugins
元该Skill帮助开发者创建OpenCode插件,用于接入命令、文件、LSP等25+种事件。它提供了插件结构、事件API规范和JavaScript/TypeScript实现模式,适合需要拦截操作、扩展功能或自定义事件处理的场景。开发者可通过它快速构建响应式模块来增强OpenCode AI助手的能力。
sglang
元SGLang是一个专为LLM设计的高性能推理框架,特别适用于需要结构化输出的场景。它通过RadixAttention前缀缓存技术,在处理JSON、正则表达式、工具调用等具有重复前缀的复杂工作流时,能实现极速生成。如果你正在构建智能体或多轮对话系统,并追求远超vLLM的推理性能,SGLang是理想选择。