generate-status-report
About
This Claude Skill generates comprehensive project status reports by analyzing existing artifacts like charters and backlogs to calculate metrics and identify blockers. It summarizes progress using RAG indicators for schedule, scope, budget, and quality. Use it at the end of sprints, before governance meetings, or when new risks emerge to provide stakeholder updates.
Quick Install
Claude Code
Recommendednpx skills add pjt222/agent-almanac -a claude-code/plugin add https://github.com/pjt222/agent-almanacgit clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/generate-status-reportCopy and paste this command in Claude Code to install this skill
Documentation
Generate a Project Status Report
Produce a periodic status report by analyzing project artifacts, calculating progress metrics, and summarizing accomplishments, blockers, and upcoming work with RAG (Red/Amber/Green) health indicators.
When to Use
- End of sprint or reporting period (weekly, biweekly, monthly)
- Stakeholder requests for project health update
- Before steering committee or governance meetings
- When project health indicators change (e.g., new blocker or risk materializes)
- Periodic checkpoint against charter milestones
Inputs
- Required: Reporting period (start date, end date)
- Required: At least one project artifact (BACKLOG.md, SPRINT-PLAN.md, WBS.md, or PROJECT-CHARTER.md)
- Optional: Previous status reports (for trend comparison)
- Optional: Budget or resource tracking data
- Optional: Risk register updates
Procedure
Step 1: Read Existing Artifacts
Scan the project directory for PM artifacts:
- PROJECT-CHARTER.md — milestones, success criteria
- BACKLOG.md — item counts by status, burn-down data
- SPRINT-PLAN.md — sprint goal, committed items, task completion
- WBS.md — work package completion percentages
- Previous STATUS-REPORT-*.md files — trend data
Read available files. Not all will exist — adapt the report to available data.
Got: At least one artifact read successfully, key metrics extracted.
If fail: If no artifacts exist, report cannot be generated. Create a charter or backlog first using the draft-project-charter or manage-backlog skills.
Step 2: Calculate Progress Metrics
Compute metrics from available data:
Agile metrics (from BACKLOG.md / SPRINT-PLAN.md):
- Velocity: story points completed this sprint
- Sprint completion: items done / items committed
- Backlog burn-down: total remaining points vs previous period
- Cycle time: average days from In Progress to Done
Classic metrics (from WBS.md):
- % complete: work packages done / total work packages
- Schedule variance: planned milestone dates vs actual
- Effort variance: estimated effort vs actual effort consumed
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
Got: 3-5 metrics calculated with previous period comparison.
If fail: If no historical data exists (first report), omit Previous and Trend columns. If data is incomplete, note gaps in report footer with action items to establish tracking.
Step 3: Identify Blockers, Risks, and Issues
List active blockers and risks:
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
Cross-reference against the charter risk register. Flag any new risks not previously identified.
Got: All active blockers and top risks documented with owners and actions.
If fail: If no blockers exist, explicitly state "No active blockers" — don't leave the section empty. If a blocker lacks an owner, escalate to project manager for assignment.
Step 4: Summarize Accomplishments and Next Period Plan
Write two sections:
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
Got: 3-5 accomplishments with concrete evidence, 3-5 planned items for next period.
If fail: If no accomplishments exist, report the reason (blocked, re-planning, team unavailable). If next period plan is unclear, list "Planning session scheduled for [date]" as the primary item.
Step 5: Assign RAG Indicators and Write Report
Assess project health across four dimensions:
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
Write the complete report:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
Save as STATUS-REPORT-[YYYY-MM-DD].md.
Got: Complete status report saved with RAG indicators, metrics, and narrative.
If fail: If data is insufficient for RAG assessment, use ⚪ (Grey) indicating "insufficient data" and list what data needs to be collected for next report.
Validation
- Status report file created with correct date-stamped filename
- RAG indicators assigned for all four dimensions with justification
- At least 3 metrics calculated from project artifacts
- Blockers section present (even if "No active blockers")
- Accomplishments listed with evidence
- Next period plan included
- Executive summary is 2-3 sentences, not a paragraph
- Every blocker and risk has an owner and action with deadline
Pitfalls
- Report without data: Status reports must be evidence-based. Every claim should reference an artifact or metric.
- All green, all the time: Persistent green RAG without evidence suggests the report isn't honest. Challenge green assessments.
- Blocker without owner: Every blocker needs an owner and an action. Unowned blockers don't get resolved.
- Metric without context: "Velocity = 18" means nothing without comparison. Include previous period or target.
- Too long: A status report should be scannable in 2 minutes. Keep it to 1-2 pages.
- Missing decisions section: If the project needs stakeholder decisions, make them explicit with deadlines.
- Stale data: Using outdated artifacts leads to misleading reports. Verify artifact dates match reporting period.
- Missing trend data: First-time reports can't show trends, but subsequent reports must compare to previous periods.
Related Skills
draft-project-charter— charter provides milestones and success criteria for status trackingmanage-backlog— backlog metrics feed the status reportplan-sprint— sprint results provide velocity and completion datacreate-work-breakdown-structure— WBS completion drives classic progress metricsconduct-retrospective— status report data feeds the retrospective
GitHub Repository
Related Skills
content-collections
MetaThis skill provides a production-tested setup for Content Collections, a TypeScript-first tool that transforms Markdown/MDX files into type-safe data collections with Zod validation. Use it when building blogs, documentation sites, or content-heavy Vite + React applications to ensure type safety and automatic content validation. It covers everything from Vite plugin configuration and MDX compilation to deployment optimization and schema validation.
polymarket
MetaThis skill enables developers to build applications with the Polymarket prediction markets platform, including API integration for trading and market data. It also provides real-time data streaming via WebSocket to monitor live trades and market activity. Use it for implementing trading strategies or creating tools that process live market updates.
creating-opencode-plugins
MetaThis skill helps developers create OpenCode plugins that hook into 25+ event types like commands, files, and LSP operations. It provides the plugin structure, event API specifications, and implementation patterns for JavaScript/TypeScript modules. Use it when you need to intercept, monitor, or extend the OpenCode AI assistant's lifecycle with custom event-driven logic.
sglang
MetaSGLang is a high-performance LLM serving framework that specializes in fast, structured generation for JSON, regex, and agentic workflows using its RadixAttention prefix caching. It delivers significantly faster inference, especially for tasks with repeated prefixes, making it ideal for complex, structured outputs and multi-turn conversations. Choose SGLang over alternatives like vLLM when you need constrained decoding or are building applications with extensive prefix sharing.