This Claude Skill automatically generates a project status report by reading project artifacts like the charter and backlog to calculate metrics and identify blockers. It summarizes progress using RAG indicators for schedule, scope, budget, and quality. Use it at the end of a sprint, before governance meetings, or when a new risk emerges.
Quick Install
Claude Code
Recommendednpx skills add pjt222/agent-almanac -a claude-code/plugin add https://github.com/pjt222/agent-almanacgit clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/generate-status-reportCopy and paste this command in Claude Code to install this skill
Documentation
Generate a Project Status Report
Periodic status: read artifacts → metrics → summary (accomplishments, blockers, next) → RAG health (sched/scope/budget/quality).
Use When
- End of sprint/period (wk/bi-wk/mo)
- Stakeholder health req
- Pre steering/governance meeting
- Health change (new blocker/risk)
- Checkpoint vs charter milestones
In
- Required: period (start, end)
- Required: ≥1 artifact (BACKLOG.md, SPRINT-PLAN.md, WBS.md, PROJECT-CHARTER.md)
- Optional: prior reports (trend)
- Optional: budget/resource data
- Optional: risk register updates
Do
Step 1: Read artifacts
Scan proj dir:
- PROJECT-CHARTER.md — milestones, success criteria
- BACKLOG.md — item counts, burn-down
- SPRINT-PLAN.md — goal, committed, task done
- WBS.md — work pkg %
- Prior STATUS-REPORT-*.md — trend
Adapt to what exists.
→ ≥1 read, key metrics extracted.
If err: no artifacts → can't generate. Create charter/backlog first via draft-project-charter or manage-backlog.
Step 2: Metrics
Agile (BACKLOG.md / SPRINT-PLAN.md):
- Velocity: pts this sprint
- Completion: done/committed
- Burn-down: remaining vs prev
- Cycle time: avg days In Progress → Done
Classic (WBS.md):
- % complete: pkgs done / total
- Schedule variance: planned vs actual
- Effort variance: est vs consumed
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
→ 3-5 metrics w/ prev comparison.
If err: no historical (first) → omit prev + trend cols. Incomplete → note gaps + track action items.
Step 3: Blockers, risks, issues
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
Cross-ref charter risk register. Flag new.
→ All blockers + top risks w/ owners + actions.
If err: no blockers → explicit "No active blockers", don't leave empty. No owner → escalate to PM.
Step 4: Accomplishments + next plan
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
→ 3-5 accomplishments w/ evidence, 3-5 planned.
If err: no accomplishments → reason (blocked, replanning, unavail). Next unclear → "Planning session scheduled for [date]".
Step 5: RAG + write
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
Write:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
Save STATUS-REPORT-[YYYY-MM-DD].md.
→ Complete report w/ RAG + metrics + narrative.
If err: insufficient for RAG → ⚪ (Grey) "insufficient data" + list data needed next report.
Check
- Report file created, date-stamped
- RAG all 4 dims w/ justify
- ≥3 metrics from artifacts
- Blockers section present (even "No active")
- Accomplishments w/ evidence
- Next plan
- Exec summary 2-3 sentences
- Every blocker/risk has owner + action + deadline
Traps
- No data: evidence-based. Every claim → artifact/metric.
- All green always: no evidence = not honest. Challenge green.
- Blocker w/o owner: no owner → not resolved.
- Metric w/o context: "Velocity=18" meaningless alone. Always prev/target.
- Too long: 2 min scan. 1-2 pages.
- Missing decisions: explicit w/ deadlines.
- Stale data: verify artifact dates match period.
- Missing trends: first-time OK, later must compare.
→
draft-project-charter— milestones + success criteriamanage-backlog— backlog metrics feed reportplan-sprint— sprint results: velocity + completioncreate-work-breakdown-structure— WBS % drives classic metricsconduct-retrospective— report data feeds retro
GitHub Repository
Related Skills
content-collections
MetaThis skill provides a production-tested setup for Content Collections, a TypeScript-first tool that transforms Markdown/MDX files into type-safe data collections with Zod validation. Use it when building blogs, documentation sites, or content-heavy Vite + React applications to ensure type safety and automatic content validation. It covers everything from Vite plugin configuration and MDX compilation to deployment optimization and schema validation.
polymarket
MetaThis skill enables developers to build applications with the Polymarket prediction markets platform, including API integration for trading and market data. It also provides real-time data streaming via WebSocket to monitor live trades and market activity. Use it for implementing trading strategies or creating tools that process live market updates.
creating-opencode-plugins
MetaThis skill helps developers create OpenCode plugins that hook into 25+ event types like commands, files, and LSP operations. It provides the plugin structure, event API specifications, and implementation patterns for JavaScript/TypeScript modules. Use it when you need to intercept, monitor, or extend the OpenCode AI assistant's lifecycle with custom event-driven logic.
sglang
MetaSGLang is a high-performance LLM serving framework that specializes in fast, structured generation for JSON, regex, and agentic workflows using its RadixAttention prefix caching. It delivers significantly faster inference, especially for tasks with repeated prefixes, making it ideal for complex, structured outputs and multi-turn conversations. Choose SGLang over alternatives like vLLM when you need constrained decoding or are building applications with extensive prefix sharing.