About

This Claude Skill helps developers create a structured release plan by defining milestones, freezes, and quality gates using either calendar-based or feature-based strategies. It generates a `RELEASE-PLAN.md` artifact to coordinate multi-team efforts and transition from ad-hoc to a formal release cadence. Use it to initiate major/minor release planning with clear go/no-go criteria and rollback procedures.

Quick Install

Claude Code

Recommended
Primary
npx skills add pjt222/agent-almanac -a claude-code
Plugin CommandAlternative
/plugin add https://github.com/pjt222/agent-almanac
Git CloneAlternative
git clone https://github.com/pjt222/agent-almanac.git ~/.claude/skills/plan-release-cycle

Copy and paste this command in Claude Code to install this skill

Documentation

Plan Release Cycle

Plan structured release cycle: pick strategy (calendar or feature), set milestones, freeze criteria, RCs, go/no-go, rollback. Output: RELEASE-PLAN.md artifact guiding team dev → release.

Use When

  • Major/minor release planning starts
  • Ad-hoc → structured release cadence
  • Multi-team or multi-component release coord
  • Quality gates + criteria for regulated project
  • First public release (v1.0.0)

In

  • Required: Target version (e.g., v2.0.0)
  • Required: Release date or window
  • Required: Planned features/scope (backlog, roadmap, desc)
  • Optional: Team size + availability
  • Optional: Strategy pref (calendar or feature)
  • Optional: Regulatory/compliance reqs
  • Optional: Past release velocity or cycle data

Do

Step 1: Determine Strategy

Two primary strategies:

Calendar-based (time-boxed):

  • Fixed schedule (e.g., 4 wks, quarterly)
  • Not-ready features → next release
  • Predictable for users + downstream
  • Best for: libraries, frameworks, tools w/ external consumers

Feature-based (scope-driven):

  • Release when defined scope done
  • Date adjusts to scope
  • Risk: scope creep, indefinite delays
  • Best for: internal tools, first releases, major rewrites

Most projects → hybrid: target date + defined scope, 1-2 week buffer. Scope not met by buffer → defer remaining.

Doc strategy choice w/ rationale.

→ Strategy doc'd w/ rationale matching project context.

If err: team can't agree → default calendar-based w/ feature-priority list. Time-box forces prioritization.

Step 2: Define Milestones

Phases w/ target dates:

## Release Plan: v2.0.0

### Timeline

| Phase | Start | End | Duration | Description |
|---|---|---|---|---|
| Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development |
| Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date |
| Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only |
| RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged |
| RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC |
| RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found |
| Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting |
| Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |

Typical durations:

  • Development: 50-70% of cycle
  • Stabilization: 15-25% of cycle
  • RC testing: 10-20% of cycle

→ Milestone table: dates, durations, descriptions per phase.

If err: timeline too compressed (stabilization < 1 wk) → extend release date or reduce scope. Never skip stabilization.

Step 3: Set Feature Freeze Criteria

Define "feature freeze" for this release:

### Feature Freeze Criteria

After feature freeze (2026-03-15):
- **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches
- **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security)
- **Exception process**: Feature freeze exceptions require written justification and approval from [release owner]

### Feature Priority List
| Priority | Feature | Status | Owner | Notes |
|---|---|---|---|---|
| P0 (must) | New export format | In progress | [Name] | Blocks release |
| P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement |
| P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready |
| P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |

P0 → blocks release. P1 → in if ready. P2 → deferred w/o delay.

→ Freeze rules doc'd w/ exception process + prioritized list.

If err: P0 at risk of missing freeze → escalate immediately. Options: extend dev phase, split feature smaller, defer to point release (v2.0.1).

Step 4: Plan RC Process

How RCs are produced + tested:

### Release Candidate Process

1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green
   ```bash
   git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
  1. RC Distribution: Publish RC to staging/testing channel

    • R: install.packages("pkg", repos = "https://staging.r-universe.dev/user")
    • Node.js: npm install pkg@next
    • Internal: Deploy to staging environment
  2. RC Testing Period: 5-7 business days

    • Run full test suite including integration tests
    • Verify all P0 features work as documented
    • Test upgrade path from previous version
    • Check for regressions in existing functionality
  3. RC Evaluation:

    • No critical/high bugs: Proceed to release
    • Critical bugs found: Fix, tag RC2, restart testing period
    • More than 2 RCs needed: Revisit scope and timeline
  4. RC2+ Tags: Only if critical issues found in previous RC

    git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
    

→ RC process doc'd: tagging convention, distribution, testing checklist, escalation.

If err: RC skipped (release pressure) → doc the risk. Untested releases → higher rollback prob.

### Step 5: Define Go/No-Go Checklist

Criteria before release approval:

```markdown
### Go/No-Go Checklist

#### Must Pass (release blocked if any fail)
- [ ] All CI checks passing on release branch
- [ ] Zero critical bugs open against this version
- [ ] Zero high-severity security vulnerabilities
- [ ] All P0 features verified and documented
- [ ] Changelog complete and reviewed
- [ ] Upgrade path tested from previous version (v1.x -> v2.0.0)
- [ ] License and attribution files up to date

#### Should Pass (release proceeds with documented risk)
- [ ] Zero high bugs open (non-critical)
- [ ] All P1 features included
- [ ] Performance benchmarks within acceptable range
- [ ] Documentation reviewed and spell-checked
- [ ] External dependencies at latest stable versions

#### Decision
- **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked
- **No-Go**: Any "Must Pass" item unchecked
- **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks

→ Go/no-go checklist w/ clear pass/fail + decision rules.

If err: meeting → no-go → ID blockers, assign owners, new target (typically 1-2 wks later), update plan.

Step 6: Document Rollback Plan

Roll back if release causes critical prod issues:

### Rollback Plan

#### Rollback Triggers
- Critical bug affecting >10% of users
- Data corruption or loss
- Security vulnerability introduced by the release
- Breaking change not documented in changelog

#### Rollback Procedure
1. **Revert package registry**: Unpublish or yank the release
   - R/CRAN: Contact CRAN maintainers (cannot self-unpublish)
   - npm: `npm unpublish [email protected]` (within 72 hours)
   - GitHub: Mark release as pre-release, publish point fix

2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels
   - Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released."

3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible

4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps

#### Point Release Policy
- v2.0.1 for critical bug fixes within 1 week of release
- v2.0.2 for additional fixes within 2 weeks
- Patch releases do not require full RC cycle but must pass CI and critical test suite

Write complete plan → RELEASE-PLAN.md or RELEASE-PLAN-v2.0.0.md.

→ Rollback plan doc'd: triggers, procedure, comm template, point release policy. Complete RELEASE-PLAN.md written.

If err: rollback not feasible (DB migration applied) → doc forward-fix instead. Every release needs recovery path.

Check

  • Strategy (calendar/feature/hybrid) doc'd w/ rationale
  • Milestone table all phases: dev, freeze, stabilization, RC, release
  • Freeze criteria w/ allowed/disallowed change types
  • Feature priority list (P0 / P1 / P2)
  • RC process doc'd: tagging, distribution, testing, escalation
  • Go/no-go has "must pass" + "should pass" sections
  • Rollback plan: triggers, procedure, comm template
  • RELEASE-PLAN.md created + saved
  • Timeline realistic (stabilization ≥ 15% of cycle)

Traps

  • No stabilization phase: Direct dev → release. Even 3-day stabilization catches issues active dev masks.
  • Scope creep after freeze: "Just one more feature" → resets testing, regression risk.
  • Ignore P0 risks: Not escalating early. Earlier scope adjust = less timeline disruption.
  • Skip RC for "small" releases: Even minor → benefit from 1 RC. Day of RC < post-release hotfix.
  • No rollback plan: Assume success. Every plan answers "what if this goes wrong?" before publish.
  • Calendar pressure > quality: Release on promised date despite failing go/no-go. Delayed release = minor inconvenience; broken release = trust violation.

  • apply-semantic-versioning — determine version for planned release
  • manage-changelog — maintain changelog feeding release notes
  • plan-sprint — sprint planning within dev phase
  • draft-project-charter — may define release roadmap + success criteria
  • generate-status-report — track progress vs milestones

GitHub Repository

pjt222/agent-almanac
Path: i18n/caveman-ultra/skills/plan-release-cycle
0
agentsagentskillsai-assisted-developmentclaude-codeskillsteams

Related Skills

executing-plans

Design

Use the executing-plans skill when you have a complete implementation plan to execute in controlled batches with review checkpoints. It loads and critically reviews the plan, then executes tasks in small batches (default 3 tasks) while reporting progress between each batch for architect review. This ensures systematic implementation with built-in quality control checkpoints.

View skill

requesting-code-review

Design

This skill dispatches a code-reviewer subagent to analyze code changes against requirements before proceeding. It should be used after completing tasks, implementing major features, or before merging to main. The review helps catch issues early by comparing the current implementation with the original plan.

View skill

connect-mcp-server

Design

This skill provides a comprehensive guide for developers to connect MCP servers to Claude Code using HTTP, stdio, or SSE transports. It covers installation, configuration, authentication, and security for integrating external services like GitHub, Notion, and custom APIs. Use it when setting up MCP integrations, configuring external tools, or working with Claude's Model Context Protocol.

View skill

web-cli-teleport

Design

This skill helps developers choose between Claude Code Web and CLI interfaces based on task analysis, then enables seamless session teleportation between these environments. It optimizes workflow by managing session state and context when switching between web, CLI, or mobile. Use it for complex projects requiring different tools at various stages.

View skill